Connection for H₂ blending

If you have already submitted a request, you can check its status here.
 
 
Connection requests for H₂ blending in the natural gas network

Here you will find…

Process steps
Description of the application process

1 – APPLICATION REGISTRATION
Register your application with the necessary information:

  • Confirmed connection point.
  • Requested capacity.
  • Final declaration of responsibility.

To complete the registration of the request, you must make a payment of €3,000 (IVA not included) for the preparation of the connection estimate.
We will review your application and, if corrections are needed, we will inform you. You will have 5 business days to amend the information.

 

2 – CAPACITY ALLOCATION
Together with the system technical manager, we will assess your request and inform you of the capacity that can be granted and its allocation status.

  • Full allocation, when the entire requested capacity is granted.
  • Partial allocation, when a lower capacity than requested is granted (it will require your explicit acceptance within a maximum of 3 business days).
  • Pending allocation, when there is no available capacity at that moment and the request remains pending possible allocation.
  • Not allocated, when there is definitively no available capacity or injection is not feasible.

 

3 – DECLARATION OF COMPLIANCE AND BUDGET APPROVAL
You must provide proof of compliance with the information stated in the declaration of responsibility within a maximum of 15 days from the date it is requested.
Once compliance is validated, we will send you the final technical and economic conditions of the connection for your acceptance.

 

4 – NEDGIA CONTRACTING AND FIRST PAYMENT
We will formalize the contract, and you must make the initial payment for the connection within a maximum of 60 days from the delivery of the technical and economic conditions.

 

5 – PROJECT, PERMITS AND WORK
We will begin processing the project, formalities and work necessary to complete the connection.

Our networks
Gas networks P>16bar
You can consult here the general diagrams with the location of our P>16bar gas networks.

Select an autonomous community:
Standard contract
Standard injection contract
Additional information
It is important that…
Prior to commissioning you must have the following documentation:
  • Accreditation of registration of the fuel gas plant in the Register of Industrial Safety Technical Installations of the corresponding Autonomous Community.
  • Accreditation of registration of the low voltage installation in the Register of Technical Installations for Industrial Safety of the corresponding Autonomous Community.

Do you need more information?