Here you will find…
1 – APPLICATION REGISTRATION
Register your application with the necessary information according to the characteristics of your needs.
2 – ACCEPTANCE AND QUOTATION
Once your application has been reviewed, we will send you a detailed quotation for the connection which you can accept.
3 – PAYMENT
You will need to pay for the network extension fees where applicable.
4 – PROJECT, PERMITS AND WORK
We will begin processing the project, formalities and work necessary to complete the connection.
5 – SUPPLY COMPANY CONTRACT AND COMMISSIONING
Once the connection has been completed, you must formalise the supply contract with your chosen supply company. You can check the official list published by the CNMC.
And if you need to get in touch with an installer using the same platform, you will have access to a section where you can find installers and request their services.
Select an autonomous community:
What does a property need to contract gas?
For each home or business premises to be able to contract a gas supply, a CUPS (Universal Supply Point Code) must be generated and activated in the gas system so that you can sign up with a supply company. We will therefore need the following information:
- Complete layout of the property (entrances, staircases, floors, flats and doors).
- Community gas installation certificates.
- Final completion certificate or first-occupancy licence.
- Documentation for the day the gas is turned on.
Once you have taken out a supply contract with the supply company, you will need to provide the following technical documentation on the day the installation is commissioned:
- RITE
- Project
- Chimney certificate