Connection for a new building

Process applications for connection to the gas network for housing developments, buildings and new-build properties.
 
 
Connection requests for new buildings

Here you will find…

Process steps
Description of the application process

1 – APPLICATION REGISTRATION
Register your application with the necessary information:

  • Plot location.
  • Information on the connection point.
  • Number of homes/premises to be connected.
  • Date on which you need us to carry out the connection work.

 

2 – ACCEPTANCE AND QUOTATION
Once your application has been accepted, we will send you a detailed quotation which you can accept.

 

3 – PAYMENT
We will finalise the agreement and you will need to make the relevant payment.

 

4 – PROJECT, PERMITS AND WORK
We will begin processing the project, formalities and work necessary to complete the connection.

Please remember to update the required connection date as we plan our work around this date. Bear in mind that if we start the process too early, permits may expire and we will have to start from scratch, which could lead to delays.

 

5 – REGISTRATION OF THE SUPPLY POINT IN THE GAS NETWORK
To ensure supply to each property, a CUPS must be generated and authorised for gas use in the gas system. To do this, you must need to provide us with:

  • Exact layout of the property. Entrances, staircases, floors, flats, doors.
  • Community gas installation certificates.
  • Final completion certificate or first-occupancy licence.
Bank account certificates
Our companies’ bank accounts
Additional information
Remember that…